Cruzio engineers have successfully completed all upstream repairs, and previously affected customers should be back online. If you continue to experience any issues, please contact our technical support team.
9/29/2023 – 9:45AM – Service Issue affecting some Wireless Pro Customers in Westside Santa Cruz area
Cruzio engineers have discovered a service issue affecting some Wireless Pro customers in Westside Santa Cruz area, and are dispatching technicians to assess the situation. We will update this status with additional information as it becomes available.
9/26/2023 10:00am – Outage in Watsonville area [RESOLVED]
A power issue at a POP site has been fixed and services should be coming back up now.
9/26/2023 8:20am – Outage in Watsonville area
Some customers in the Watsonville area may be experiencing an outage. Engineers are currently investigating the cause and will post updates if we get more information before the problem is fixed.
9/21/23 9AM-6PM – Maintenance affecting some Wireless Pro customers in Watsonville
Cruzio engineers will be performing planned maintenance on upstream equipment serving some Wireless Pro customers in Watsonville on Thursday, 9/21/23 9AM-6PM . Affected customers may experience brief periods of downtime as our technicians complete this work.
9/14/2023 11am – Power Outages in Scotts Valley area [RESOLVED]
PG&E has completed it’s work much earlier than anticipated so we expect no more outages.
9/14/2023 8:20am – Power Outages in Scotts Valley area
Due to power outages in the Scotts Valley area, there may be some loss of services during the day. Crews are working to set up generators to keep services running, but there may be some outages while those fixes are being implemented. We will post updates as we get more information.
9/13/23 10PM-2AM – Emergency Maintenance affecting some Wireless Pro customers in Westside Santa Cruz
Cruzio engineers will be conducting maintenance on upstream equipment serving a part of Westside Santa Cruz on Wednesday, 9/13/2023 from 10pm to 2am. Affected customers may experience brief periods of downtime during this process. Technicians will keep interruptions as minimal as possible.
9/12/23 10:00PM-4:00AM – Maintenance affecting some Wireless customers in the Live Oak area
Cruzio engineers will be performing planned maintenance for some Wireless Pro services in the Live Oak area Tuesday, 9/12/23 10PM-4AM . Affected customers may experience brief periods of downtime as our technicians complete this work.
9/5/2023 4:33PM – Service Interruption for Customers at Nanda Apartments [COMPLETE]
Emergency maintenance at Nanda Apartments is now complete. Thank you for your patience.